The 600 mm Deck: Toronto vs. Brampton
See how Toronto and Brampton treat the same 600 mm deck, where to measure its height, and what to check before you ask for a quote.
This article contains affiliate links. BuildRules may earn a commission if you buy through these links. As an Amazon Associate I earn from qualifying purchases.
A 3 m by 3 m freestanding deck, uncovered and exactly 600 mm above the adjacent finished ground, is our test case. It serves no required exit, and we assume it meets the zoning rules for the lot. At that height, Brampton requires a building permit. In Toronto, the deck can fit the city's published example of work exempt from a building permit if the other conditions are met.
Same deck, two results
Toronto: may qualify for an exemption. Toronto's building permit guidance (opens in a new tab) includes an uncovered platform whose finished level is no more than 60 cm above the adjacent finished ground. The guidance also references required exits and zoning. This example assumes the deck is outside any required exit route and the location meets the applicable zoning by-law. For a real lot, ask Toronto Building to confirm the result before relying on the exemption.
Brampton: a building permit is required. Brampton's deck guidance (opens in a new tab) includes 0.6 m in its permit-required range. The city also requires a permit if the deck is attached or anchored to the house, even below 0.6 m. Check setbacks and any permitted encroachment for the lot.
What if you lower the deck?
At 550 mm, the same freestanding deck is below Brampton's height trigger. It can fit Brampton's published no-permit example if it remains detached and meets the applicable zoning rules. If you attach or anchor it to the house, Brampton's attachment rule changes the answer. If you add a roof or make the deck part of a required exit, ask the city to reassess the proposed work.
Take three notes before asking for a quote
- Height. Measure vertically from the planned top of the deck boards to the adjacent finished ground. Use millimetres, record the corners and note the largest difference on sloping ground. Ask the city how it wants the grade shown if you plan to change it.
- Connection. Mark whether the deck has its own supports or is physically fixed to the house. Show any stairs, roof or exit the deck would serve.
- Location. Mark the deck footprint and the distances to the property lines on your sketch. Give the city the address and ask what setbacks and permit steps apply to that lot.
Use a tape measure with readable metric markings. If you need a replacement, compare tape measures on Amazon.ca (affiliate link) (opens in a new tab) and check the listing photos for metric graduations before you buy.
Start the deck pre-check or compare deck permit rules across Ontario.
Project conditions and next steps
Conditions that can change the answer
- Example: freestanding and uncovered 3 m × 3 m deck, exactly 600 mm above adjacent finished grade.
- Toronto example assumes zoning compliance and that the deck does not form part of a required exit.
- Brampton includes 600 mm in the permit-required range and separately requires a permit for a deck attached or anchored to the house.
What to do next
- Mark the finished deck surface height, attachment and lot-line distances on the same sketch.
- Ask the municipal building division to confirm the permit and zoning steps for the actual address.
Questions & answers
Is 24 inches exactly 600 mm?
No. Exactly 24 inches is 609.6 mm. The cities give rounded imperial equivalents in their guidance. Near the threshold, record the actual measurement in millimetres and ask the city to confirm how it applies the rule to your site.
Tools mentioned in this guide
Choose by the task you need to do. Use what you own or borrow first, then compare options if something is missing.
This article contains affiliate links. BuildRules may earn a commission if you buy through these links. As an Amazon Associate I earn from qualifying purchases.
Measuring tape
Amazon.ca- Useful for
- Measure preliminary dimensions; use an existing tape first.
- Check before choosing
- Length, readable markings and metric or imperial units.
Sources & references
- Toronto | When Do I Need a Building Permit? (opens in a new tab)
- Brampton | Decks, Porches and Patios (opens in a new tab)