Permit decision · Official evidence
What the municipality actually requires.
These are general rules and exceptions, not approval for your address. Review the conditions and open the original sources before starting work.
Barrie’s addition guide covers increases in building area or storeys. A small addition is still an addition; the City does not give it a size exemption in this guide.
Source · City of Barrie
Building an Addition — Quick Start Guide · Permit trigger, corner lots, septic review and applicable charges; March 6, 2024
Source checked Oct 7, 2026Open official sourceBarrie specifically flags corner-lot sight triangles, zoning and conservation-authority requirements. Ask the City which setbacks, height and other property controls apply to the proposed footprint.
Source · City of Barrie
Building an Addition — Quick Start Guide · Permit trigger, corner lots, septic review and applicable charges; March 6, 2024
Source checked Oct 7, 2026Open official sourceBarrie says properties on private septic need a review of the existing system for Building Code compliance when planning an addition.
Source · City of Barrie
Building an Addition — Quick Start Guide · Permit trigger, corner lots, septic review and applicable charges; March 6, 2024
Source checked Oct 7, 2026Open official sourceThe City’s Allandale guidance identifies review for additions over 10 m², height increases and street-facing façade changes in the affected area, with limited rear-yard exemptions. Confirm the address and proposal with Planning; this is separate from the building permit.
Source · City of Barrie
Allandale Historic Neighbourhood — Heritage Design Guidelines · Scoped site plan review in the identified area; confirm current property applicability
Source checked Oct 7, 2026Open official sourceNext step · Applications and documents
How to apply and what to prepare.
These are filing instructions and preparation checks. They do not prove a building permit is required or exempted for your property.
Open the City’s application list below and choose Building Permit for residential work. Describe the addition and connected alterations together; submitting an application is not permission to start building.
Source · City of Barrie
APLI — Permit application types · Building Permit: residential applications
Source checked Oct 7, 2026Open official sourceBarrie’s residential checklist includes site, floor, foundation, framing, elevation and section drawings, plus an energy summary expressly covering additions. It is headed “New Residential Dwelling Unit”: use it as a preparation reference, not proof that every new-build item applies to an existing-house addition.
Source · City of Barrie
New Residential Dwelling Unit — Building Permit Application Checklist · Residential drawing reference; energy summary expressly includes additions. Confirm the addition-specific package with Barrie; September 17, 2025
Source checked Oct 7, 2026Open official sourceApproved Schedule K item 1.5.1 includes basement area. The Part 9 residential minimum is $178.48; the schedule also lists a $20 non-refundable pre-screening fee. Additional charges depend on scope. Ask Barrie to calculate the payable total.
Source · City of Barrie
Schedule K — Building Services, approved 2026 fees · Items 1.1.1, 1.1.2, 1.5.1 and fee calculation notes
Source checked Oct 7, 2026Open official sourceOntario gives 10 days as the house-permit review example when a complete application meets Code criteria. This is a decision period, not guaranteed approval or total project duration. The permit holder must arrange municipal inspections at required stages.
Source · Province of Ontario
Citizen’s guide to land use planning — Building permits · Complete-application review, applicable law and construction inspections
Source checked Oct 7, 2026Open official sourceMake a start
Your preparation checklist
Home addition
Planning record, not municipal approval. Confirm the conditions and official requirements for your property.
0 of 6 ready
Your progress is saved in this browser. Project reference, date and notes stay in this tab until you leave.
Plan ahead
Fees and timing
Review timeline
Ontario’s guide gives a 10-day review example for a complete house-permit application meeting Code criteria.
Read all timing details
It is a permit decision period, not a Barrie end-to-end delivery promise. Design, missing information, zoning relief and other approvals add time.
Permit fees
2026 approved Schedule K: Part 9 residential additions $17.38/m² (including basement); $178.48 minimum; $20 non-refundable pre-screening fee.
Read all fee conditions
Example: 30 m² × $17.38 = $521.40 base area fee, before pre-screening and applicable extras. Confirm the assessed area and charges with Barrie; this is not a quote.
Project calculators and printable worksheets
Record the scope and compare quotes
Free worksheets to fill in or print. Confirm the applicable requirements with the municipality.
From reading to doing
Your next steps.
Follow the practical steps in the published Barrie guide. Confirm unresolved details with the City before committing to work.
Define rear/side extension or extra storey, proposed floor area and any work inside the existing house.
Contact Service Barrie at 705-726-4242 or Service.Barrie@barrie.ca to confirm the addition checklist and property approvals before paying for final plans.
Have your designer resolve site constraints and prepare coordinated drawings; arrange septic review if relevant.
Use the City’s APLI Building Permit application. Address review comments and pay applicable amounts before issuance.
Begin construction after permit issuance, keep approved plans on site and arrange the required inspections with Barrie.
Trace the evidence
Official sources behind this guide.
These are the source documents linked in the rules above. Check the municipal authority for current requirements before submitting a project.
- City of Barrie
Building an Addition — Quick Start Guide · Permit trigger, corner lots, septic review and applicable charges; March 6, 2024
Source checked Oct 7, 2026
- City of Barrie
APLI — Permit application types · Building Permit: residential applications
Source checked Oct 7, 2026
- City of Barrie
Allandale Historic Neighbourhood — Heritage Design Guidelines · Scoped site plan review in the identified area; confirm current property applicability
Source checked Oct 7, 2026
- City of Barrie
New Residential Dwelling Unit — Building Permit Application Checklist · Residential drawing reference; energy summary expressly includes additions. Confirm the addition-specific package with Barrie; September 17, 2025
Source checked Oct 7, 2026
- City of Barrie
Schedule K — Building Services, approved 2026 fees · Items 1.1.1, 1.1.2, 1.5.1 and fee calculation notes
Source checked Oct 7, 2026
- Province of Ontario
Citizen’s guide to land use planning — Building permits · Complete-application review, applicable law and construction inspections
Source checked Oct 7, 2026
A little more clarity
Common questions.
Does a small rear extension need a permit in Barrie?
Yes. The City’s addition guide says every addition needs a building permit. Increasing the footprint is an addition even if the room is small.
What changes for a second-storey addition?
An extra storey is expressly covered by Barrie’s addition definition. Have the designer assess the existing structure and ask the City about property height limits and required drawings.
Is removing a wall the same permit scope?
Wall removal without increasing area or storeys is not the addition described here. Give Barrie the exact structural and interior scope rather than treating this guide as an exemption.
Do Allandale properties have another review?
They can. Barrie publishes scoped site plan guidance for the identified historic area. Confirm whether the property and addition are affected before finalizing the design.
Are development charges always payable?
No blanket amount is established here. Barrie’s addition guide lists development and education charges, parkland dedication and water-meter payments where applicable. Ask which apply to your proposal.
Can I book construction for 10 days after applying?
Do not treat Ontario’s complete-application review example as a guaranteed start date. A refusal, missing documents or other approvals can change the schedule. Wait for the issued permit.
More permit definitions and related guides
Know the approval terms
The permit decision can involve more than one rule.
Use these plain-language definitions to understand the conditions above, then check the official source for your municipality.
Setback
A setback is the required distance between a building or structure and a property line, street, another feature or another regulated reference point.
Lot coverage
Lot coverage is a zoning measurement describing how much of a lot is occupied by buildings or structures under the applicable municipal rules.
Minor variance
An approval route through a municipality’s Committee of Adjustment for certain proposals that do not comply with the zoning by-law.
Same project, different city
See how this rule changes across Ontario.
Compare the source-reviewed answer for this project across every municipality BuildRules currently covers.
Compare home addition rules by cityProfessional help
Find help with your home addition in Barrie.
Review the available options by city and project. Only a business with a claimed BuildRules profile can receive a direct referral, and responses are never guaranteed.
Get help with home addition