Municipal evidence · Last verified Nov 18, 2026
Include the new basement area in your Barrie estimate
In Barrie’s 2026 Part 9 schedule, a hypothetical addition with 12 m² upstairs and 12 m² of new basement has a 24 m² billing area if Barrie accepts those dimensions. At $17.38 per m², the area charge is $417.12. For an 8 m² addition without a basement, the area charge would be $139.04, so the $178.48 minimum would apply.
City of Barrie — official requirements
What still needs checking for your property: Both examples isolate the permit charge. The schedule lists a separate $20 non-refundable pre-screening fee. Ask Barrie for the assessed area, applicable charges and the total when you apply.
Scope before arithmetic
Make sure the fee belongs to your project.
A rear room extension and a second-storey addition both fall within Barrie’s addition definition. Permit approval also depends on zoning and applicable law. On a corner lot, check sight triangles; on private septic, arrange a qualified designer’s review. Interior-only work needs its own scope assessment.
Barrie’s addition guide covers increases in building area or storeys. A small addition is still an addition; the City does not give it a size exemption in this guide.
Open the City’s application list below and choose Building Permit for residential work. Describe the addition and connected alterations together; submitting an application is not permission to start building.
Barrie specifically flags corner-lot sight triangles, zoning and conservation-authority requirements. Ask the City which setbacks, height and other property controls apply to the proposed footprint.
Official sources behind this page
Barrie’s addition guide covers increases in building area or storeys. A small addition is still an addition; the City does not give it a size exemption in this guide.
Open the City’s application list below and choose Building Permit for residential work. Describe the addition and connected alterations together; submitting an application is not permission to start building.
Barrie specifically flags corner-lot sight triangles, zoning and conservation-authority requirements. Ask the City which setbacks, height and other property controls apply to the proposed footprint.
Barrie says properties on private septic need a review of the existing system for Building Code compliance when planning an addition.
The City’s Allandale guidance identifies review for additions over 10 m², height increases and street-facing façade changes in the affected area, with limited rear-yard exemptions. Confirm the address and proposal with Planning; this is separate from the building permit.
Barrie’s residential checklist includes site, floor, foundation, framing, elevation and section drawings, plus an energy summary expressly covering additions. It is headed “New Residential Dwelling Unit”: use it as a preparation reference, not proof that every new-build item applies to an existing-house addition.
Approved Schedule K item 1.5.1 includes basement area. The Part 9 residential minimum is $178.48; the schedule also lists a $20 non-refundable pre-screening fee. Additional charges depend on scope. Ask Barrie to calculate the payable total.
Ontario gives 10 days as the house-permit review example when a complete application meets Code criteria. This is a decision period, not guaranteed approval or total project duration. The permit holder must arrange municipal inspections at required stages.
Need the full project answer?
The main guide keeps the permit trigger, zoning questions, documents, fees, timing and next steps together.
Open the home addition guide