Mississauga project guide

What do you need to create a basement apartment or second unit in Mississauga?

Mississauga basement apartment and ARU permit fees for 2026: $11.33/m² plus minimum fee, refundable permit charges after inspections and free second-unit registration.

4 min readMunicipal source reviewed Oct 14, 2026
Editorial illustration of a basement apartment / secondary suite project
Project illustration; not an assessed property or an approved design.
The short answerConditional

A new or converted second unit needs the applicable building permit work and must meet Building Code, Fire Code and zoning requirements; second units are also registered with the City.

Understand the conditions in detail

Mississauga treats an additional residential unit as more than a basement finish. Conversion drawings, applicable-law information and registration are part of the route.

Conditions and exceptions to check

  • Permit: Building permit route applies
  • Registration: Required for second units

Official source

Next step

Confirm the property and unit configuration

Municipal guidance only. Your property's zoning and other applicable approvals may change the result.

BUILDRULES / MISSISSAUGA

Share Mississauga guidance

Send the answer with its source and review date. No property address is included.

Mississauga / Basement apartment / secondary suite

A new or converted second unit needs the applicable building permit work and must meet Building Code, Fire Code and zoning requirements; second units are also registered with the City.

City of Mississauga · BuildRules reviewed 2026-10-14

Mississauga project paths

A basement apartment, or another kind of renovation?

Choose the actual work before you plan the permit application. Different scopes can need different drawings, professionals and approvals.

These are published Mississauga municipal guides, not a property assessment or approval. Confirm the proposed work and current requirements with official sources before starting.

Project navigator / MississaugaCompare project paths before you commit.Find the guide for the work you actually plan, then compare it with this project.Open navigator
1What are you changing inside the basement?

Choose one scope to start. If your renovation includes several, review each applicable guide.

Only guides with current source records in the BuildRules catalogue are shown. Other scopes may still require municipal confirmation; absence from this list does not mean an exemption.

Permit decision · Official evidence

What the municipality actually requires.

These are general rules and exceptions, not approval for your address. Review the conditions and open the original sources before starting work.

PermitBuilding permit route appliesConditional

Mississauga lists basement apartments among permit-required projects and publishes an ARU conversion submission checklist.

Source · City of Mississauga

When a building permit is required · Permit-required and permit-exempt project examples

Source checked Oct 26, 2026Open official source
RegistrationRequired for second unitsConditional

Mississauga states that second units must meet code and zoning requirements and be registered with the City.

Source · City of Mississauga

Registering a second unit · Free registration of a second unit; proof of ownership, signed-off permit and registration form

Source checked Oct 14, 2026Open official source
ARU building-permit fee rebateRefunded after final inspectionsConditional

The City says eligible building permit fees are automatically refunded after an ARU is constructed or legalized and all required inspections are complete. Expect other design, construction and property-specific charges.

Source · City of Mississauga

Additional residential units: permit fee rebate and 2026 requirements · Building permit fee rebate, permit fees and charges, refund after all inspections, review time, zoning limitations

Source checked Oct 14, 2026Open official source

Next step · Applications and documents

How to apply and what to prepare.

These are filing instructions and preparation checks. They do not prove a building permit is required or exempted for your property.

Conversion documentsDedicated checklist

The City requires project-specific forms and drawings when converting existing space into a second, third or fourth unit.

Source · City of Mississauga

Additional residential unit conversions · Second, third and fourth unit conversion documents

Source checked Oct 1, 2026Open official source
2026 ARU permit charges$11.33/m² plus minimum residential fee

Schedule B (2026) lists $11.33 per m² for an additional residential unit within an existing building plus the minimum residential fee; the Part 9 residential minimum is $244. Final amount depends on the permit scope and area confirmed by the City.

Source · City of Mississauga

2026 Classes of Permits and Fees, Building By-law 0236-2024 Schedule B · Schedule B (PDF p. 1): Part 9 residential $244 minimum and Group C additional residential unit within an existing building $11.33/m² plus minimum residential fee

Source checked Oct 14, 2026Open official source
Second-unit registrationFree

The City charges no fee to register a second unit, but requires proof of ownership, signed-off building-permit evidence and a completed registration form.

Source · City of Mississauga

Registering a second unit · Free registration of a second unit; proof of ownership, signed-off permit and registration form

Source checked Oct 14, 2026Open official source

Take it with you

Prepare the project and compare written quotes.

Free working documents to fill in or print. Confirm the applicable requirements with the municipality.

Make a start

Your preparation checklist

buildrules.caPROJECT PREPARATION

Basement apartment / secondary suite

Planning record, not municipal approval. Confirm the conditions and official requirements for your property.

Your preparation progress

0 of 5 ready

Your progress is saved in this browser. Project reference, date and notes stay in this tab until you leave.

Guide : buildrules.ca/mississauga/secondary-suite-permit · Sources reviewed 2026-10-14

Open the focused permit checklist

Plan ahead

Fees and timing

Review timeline

For a complete application, Mississauga indicates that the first permit review may take 15 business days.

Read all timing details

Incomplete submissions and re-submissions can add two weeks or more; this is not a guaranteed permit-issuance timeline.

Permit fees

Mississauga Building By-law 0236-2024 Schedule B (2026) lists an $11.33/m² rate for an additional residential unit inside an existing building, plus the minimum residential fee ($244 for Part 9 projects).

Read all fee conditions

The City calculates the final upfront building-permit charge after reviewing the type and size of the proposed unit. Critically, Mississauga says eligible permits for building or legalizing an ARU are automatically refunded after construction and all required inspections are complete. Registration of a second unit is free. Other costs can remain, including drawings, renovations, fire inspections, some development charges for additions or garden suites, and a $81.90 + HST address fee for garden suites where applicable. Confirm rebate eligibility and all charges for your property with the City.

From reading to doing

Your next steps.

Follow the practical steps in the published Mississauga guide. Confirm unresolved details with the City before committing to work.

  1. Confirm the property and unit configuration

  2. Prepare conversion drawings

  3. Apply for the building permit

  4. Complete inspections and registration requirements

Trace the evidence

Official sources behind this guide.

These are the source documents linked in the rules above. Check the municipal authority for current requirements before submitting a project.

  • City of Mississauga

    When a building permit is required · Permit-required and permit-exempt project examples

    Source checked Oct 26, 2026

  • City of Mississauga

    Additional residential unit conversions · Second, third and fourth unit conversion documents

    Source checked Oct 1, 2026

  • City of Mississauga

    Registering a second unit · Free registration of a second unit; proof of ownership, signed-off permit and registration form

    Source checked Oct 14, 2026

  • City of Mississauga

    2026 Classes of Permits and Fees, Building By-law 0236-2024 Schedule B · Schedule B (PDF p. 1): Part 9 residential $244 minimum and Group C additional residential unit within an existing building $11.33/m² plus minimum residential fee

    Source checked Oct 14, 2026

  • City of Mississauga

    Additional residential units: permit fee rebate and 2026 requirements · Building permit fee rebate, permit fees and charges, refund after all inspections, review time, zoning limitations

    Source checked Oct 14, 2026

A little more clarity

Common questions.

Does a basement apartment need a permit in Mississauga?

Mississauga lists basement apartments among permit-required projects and publishes a dedicated additional-residential-unit conversion checklist.

Is a basement finish the same as an ARU in Mississauga?

No. Creating another dwelling unit uses the ARU conversion route, while ordinary basement finishing follows a separate permit path.

Does a second unit need to be registered in Mississauga?

Yes. Mississauga states that second units must meet applicable code and zoning requirements and be registered with the City.

What does a Mississauga additional residential unit building permit cost in 2026?

The 2026 Schedule B lists $11.33/m² for an additional residential unit within an existing building, plus the minimum residential fee ($244 for residential Part 9 work). The City calculates the exact upfront amount after assessing the proposed project. Qualifying ARU building-permit fees are refunded after construction and all required inspections are completed.

Are Mississauga ARU building permit fees refunded?

Mississauga says a building permit fee for building or legalizing an additional residential unit is automatically refunded after the ARU is built and all required building inspections are completed. The City mails a refund cheque. Other charges such as drawings, construction, applicable development charges and some service fees are separate.

Is there a fee to register a second unit in Mississauga?

No. Mississauga says registration of a second unit is free. Owners must provide proof of ownership, a signed-off building permit or obtain a permit if missing, and the registration form.

How long does Mississauga take to first-review an ARU permit?

The City says the first review of a complete ARU permit application may take 15 business days. Re-submissions can add two weeks or more; this is not an approval-time guarantee.

Know the approval terms

A second unit can meet one rule and still need another approval.

Building permits, zoning and applicable law are separate parts of the approval path.

Same project, different city

See how this rule changes across Ontario.

Compare the source-reviewed answer for this project across every municipality BuildRules currently covers.

Compare basement apartment / secondary suite rules by city

Professional help

Find help with your basement apartment / secondary suite in Mississauga.

Review the available options by city and project. Only a business with a claimed BuildRules profile can receive a direct referral, and responses are never guaranteed.

Get help with basement apartment / secondary suite

When you need a hand

Choose your next step.

Keep preparing on your own, get a research brief, or ask for professional help.

BuildRules / Preparation briefFree report

Before your first contractor quote

Bring the right questions to the conversation.

Collect the published local guidance, documents to prepare and unresolved property questions in one brief you can send or print.

01 Permit and local-rule guidance02 Documents to prepare03 Questions still to verify
Prepare my free project brief

Read and print the brief on screen. Email a copy optionally. Newsletter optional. This is guidance, not municipal approval.

Professional help

Bring the right people into your project.

Need drawings, engineering or a quote? Tell us what you need and we’ll save your request with the project context.

Request project help

A little help with the next step

Move your basement apartment / secondary suite forward.

Tell us what kind of help you need. BuildRules saves your project request for review. This form does not send your details directly to a listed professional.

Your request goes to BuildRules, not directly to a contractor. Municipal approval stays with the City.

A provider match is not guaranteed. Municipal approval stays with the City.