Burlington project guide

What do you need for an additional residential unit in Burlington?

Check Burlington additional residential unit requirements, including building permits, zoning, application screening and the published 10-business-day review target.

1 min readReviewed Oct 1, 2026
The short answerConditional

Burlington requires a building permit for ARU construction and requires the application to meet zoning and performance standards for the property.

The City publishes a step-by-step ARU process with a two-business-day screening target and a 10-business-day building-permit review once the application is complete.

Make this useful for my project

Know what matters

What changes the answer.

Start with these conditions. The official reference is attached to each one.

Building permitRequiredConditional

Burlington states that creating one, two or three ARUs requires a building permit for the applicable renovation, addition or accessory building.

Official sourceCity of BurlingtonAdditional Residential Units · ARU building permit and zoning requirements
Verified2026-10-01Open proof
ZoningMust meet applicable standardsConditional

The ARU application must meet the City’s zoning regulations and performance standards.

Official sourceCity of BurlingtonAdditional Residential Units · ARU building permit and zoning requirements
Verified2026-10-01Open proof
Screening and review2-day screening; 10-day review after complete applicationInfo

Burlington publishes a two-business-day screening target and a 10-business-day permit review target for a complete ARU application.

Official sourceCity of BurlingtonSteps to Build an Additional Residential Unit · Application screening, review, construction and occupancy
Verified2026-10-01Open proof

Your preparation checklist

Your preparation progress

0 of 5 ready

Your progress is saved in this browser. Come back whenever you’re ready.

Open the focused permit checklist

Fees and timing

TimelineBurlington states that it screens an ARU application within 2 business days and reviews/Issues the building permit within 10 business days once the application is complete.

Open the focused timeline

FeesConfirm the current Burlington fee schedule for the exact permit class.

Next steps

  1. Confirm which ARU type is proposed
  2. Check zoning/property eligibility
  3. Prepare and submit the complete building permit package
  4. Respond to deficiencies and complete inspections/occupancy

Same project, different city

See how this rule changes across Ontario.

Compare the source-reviewed answer for this project across every municipality BuildRules currently covers.

Compare additional residential unit rules by city

Better decisions, together

Get everyone on the same page.

Send this to your designer or contractor before agreeing on the scope.