Focused project answerLast verified Nov 9, 2026
Published fee information

Whitby 2026 Schedule N BGP-45 Change of Use: $305 flat (all categories, no HST), excluding additional alteration/occupancy/site approvals or professional design costs.

Use this as a municipal-fee reference, not as the total project budget. Design, engineering, related applications and construction costs are separate.

Scope before arithmetic

Make sure the fee belongs to your project.

Changing use can alter Building Code occupancy/hazard classification, allowable zoning, exits, fire protection and accessibility even where no construction is planned. Review current legally approved use and proposed activity with Whitby Building Services (building@whitby.ca). The Town's permit submission table does not list a separate E-Portal Change of Use workflow; obtain the correct filing instructions directly instead of assuming the standard residential alteration flow.

Permit decisionChange of Use permit, zoning and fire-safety review

Changing use can alter Building Code occupancy/hazard classification, allowable zoning, exits, fire protection and accessibility even where no construction is planned. Review current legally approved use and proposed activity with Whitby Building Services (building@whitby.ca). The Town's permit submission table does not list a separate E-Portal Change of Use workflow; obtain the correct filing instructions directly instead of assuming the standard residential alteration flow.

Application route, if a permit appliesConfirm correct Change of Use filing with Building Services

Identify existing lawful use and proposed new use. Ask Building Services if use change triggers permit even without building alterations and whether zoning permits the new activity. Prepare occupancy, exit, fire, accessibility and any construction documentation. Ask Town staff which Change of Use submission channel applies; it is not a separately listed E-Portal category. Budget the $305 BGP-45 fee plus separate approved work and wait for written permission before occupancy.

Local checks and submission documents2026 BGP-45 $305 flat, other approvals may add costs

Existing lawful and proposed occupancy/use at property; Building floor area, planned occupants and layout; Exits, fire protection and accessibility considerations; Any accompanying renovation/structural or mechanical work; Current property zoning and any separate approvals

Official sources behind this page

Permit decisionChange of Use permit, zoning and fire-safety review

Changing use can alter Building Code occupancy/hazard classification, allowable zoning, exits, fire protection and accessibility even where no construction is planned. Review current legally approved use and proposed activity with Whitby Building Services (building@whitby.ca). The Town's permit submission table does not list a separate E-Portal Change of Use workflow; obtain the correct filing instructions directly instead of assuming the standard residential alteration flow.

Official sourceTown of WhitbyBuilding Permits: applications, mandatory documents, E-Portal submission by type · 2026 permit categories, applicable law checklist, submissions, inspections
Verified2026-11-09Open proof
Application route, if a permit appliesConfirm correct Change of Use filing with Building Services

Identify existing lawful use and proposed new use. Ask Building Services if use change triggers permit even without building alterations and whether zoning permits the new activity. Prepare occupancy, exit, fire, accessibility and any construction documentation. Ask Town staff which Change of Use submission channel applies; it is not a separately listed E-Portal category. Budget the $305 BGP-45 fee plus separate approved work and wait for written permission before occupancy.

Official sourceTown of WhitbyBuilding Permits: applications, mandatory documents, E-Portal submission by type · 2026 permit categories, applicable law checklist, submissions, inspections
Verified2026-11-09Open proof
Local checks and submission documents2026 BGP-45 $305 flat, other approvals may add costs

Existing lawful and proposed occupancy/use at property; Building floor area, planned occupants and layout; Exits, fire protection and accessibility considerations; Any accompanying renovation/structural or mechanical work; Current property zoning and any separate approvals

Official sourceTown of WhitbySchedule N to By-law 7220-17: 2026 Building Services Fees · BGP-73 below grade entrance $305 flat, BGP-55 $305 minimum, January 1 2026
Verified2026-11-09Open proof
2026 permit fee reference2026 Change of Use permit fee: $305 flat

Town Schedule N BGP-45 lists a $305 flat fee, no HST, for Change of Use applications. This is only the City building-permit charge; work needed to meet new occupancy requirements may trigger other fees.

Official sourceTown of WhitbySchedule N to By-law 7220-17: 2026 Building Services Fees · BGP-73 below grade entrance $305 flat, BGP-55 $305 minimum, January 1 2026
Verified2026-11-09Open proof
Change of Use is not a renovation exemptionOccupancy changes can need permission without any construction

Whitby lists Change of Use as permit-required and publishes a distinct BGP-45 flat fee, but zoning, fire and other occupancy standards still apply.

Official sourceTown of WhitbyBuilding Permits: applications, mandatory documents, E-Portal submission by type · 2026 permit categories, applicable law checklist, submissions, inspections
Verified2026-11-09Open proof

Need the full project answer?

The main guide keeps the permit trigger, zoning questions, documents, fees, timing and next steps together.