Plan the stages separately
The published period is not the whole project.
Vaughan generally lists 10 business days to process a complete single-family dwelling permit application. This is a processing benchmark, not a guaranteed issuance date or the time required for grading, zoning, variances, engineering or other approvals. Incomplete applications are excluded from this benchmark.
Official sources behind this page
Vaughan states that an addition requires a building permit before construction.
The City directs applicants to obtain a Development Engineering Grading Permit first.
Vaughan publishes separate grading fees for additions above and below 40 m².