What the municipality actually requires.
These are general rules and exceptions, not approval for your address. Review the conditions and open the original sources before starting work.
Toronto's New House guide applies to new detached houses, semis and row houses.
Source · City of Toronto
New House · Permit route, site plan, grading, drawings, forms and 2026 fees
Source checked Oct 1, 2026Open official sourceThe site plan must show setbacks, coverage, grade and other permitted and proposed zoning information.
Source · City of Toronto
New House · Permit route, site plan, grading, drawings, forms and 2026 fees
Source checked Oct 1, 2026Open official sourceFor a proposed new fourplex or sixplex, Toronto provides free narrow/wide designs. Permit issuance still requires the appropriate multiplex application, qualified design professional, site-specific drawings and zoning review. Alterations, including HVAC/plumbing changes, remove pre-approved status.
Source · City of Toronto
Pre-Approved Multiplex Building Plans · Fourplexes and sixplexes
Source checked Oct 23, 2026Open official sourceNext step · Applications and documents
How to apply and what to prepare.
These are filing instructions and preparation checks. They do not prove a building permit is required or exempted for your property.
Related plumbing, drain and mechanical permits can be submitted with the new-house application.
Source · City of Toronto
New House · Permit route, site plan, grading, drawings, forms and 2026 fees
Source checked Oct 1, 2026Open official sourceToronto permits fourplexes citywide under applicable zoning conditions; permission for sixplexes varies by area. This New House guide is not automatically the multiplex permit pathway.
Source · City of Toronto
Multiplex Housing — zoning and geographic eligibility · Citywide fourplexes and area-specific sixplexes
Source checked Oct 23, 2026Open official sourceTake it with you
Prepare the project and compare written quotes.
Free working documents to fill in or print. Confirm the applicable requirements with the municipality.
Make a start
Your preparation checklist
New house
Planning record, not municipal approval. Confirm the conditions and official requirements for your property.
0 of 6 ready
Your progress is saved in this browser. Project reference, date and notes stay in this tab until you leave.
Plan ahead
Fees and timing
Review timeline
New-house reviews are more involved than minor residential permits. Confirm the current service standard after the scope and zoning path are established.
Permit fees
Toronto lists a 2026 residential construction rate of $18.56/m² for single-family dwellings, semis, townhouses, duplexes and live/work units, plus applicable unit and related-permit fees.
From reading to doing
Your next steps.
Follow the practical steps in the published Toronto guide. Confirm unresolved details with the City before committing to work.
Confirm zoning feasibility
Commission current survey and grading information
Coordinate architectural and structural design
Prepare related plumbing and HVAC submissions
For a new fourplex or sixplex, compare Toronto's pre-approved designs, verify zoning at the address, and have a qualified professional confirm the correct multiplex permit documents before paying for custom plans.
Trace the evidence
Official sources behind this guide.
These are the source documents linked in the rules above. Check the municipal authority for current requirements before submitting a project.
- City of Toronto
New House · Permit route, site plan, grading, drawings, forms and 2026 fees
Source checked Oct 1, 2026
- City of Toronto
Pre-Approved Multiplex Building Plans · Fourplexes and sixplexes
Source checked Oct 23, 2026
- City of Toronto
Multiplex Housing — zoning and geographic eligibility · Citywide fourplexes and area-specific sixplexes
Source checked Oct 23, 2026
A little more clarity
Common questions.
Do I need zoning information before designing a new house?
Yes. The City's required site-plan information includes permitted and proposed zoning provisions, so early zoning review can prevent redesign.
Does a new house need an energy form?
Yes for applicable Part 9 residential construction, the City guide identifies an Energy Efficiency Design Summary as part of the submission.
What permit do you need to build a new house in Toronto?
A building permit is required to construct a new detached, semi-detached or row house in Toronto.
Can I build a fourplex or sixplex using Toronto's free pre-approved plans without a building permit?
No. The free plans are pre-reviewed building designs, not site approval. You still need a permit and a qualified design professional to complete site-specific documentation. Fourplex permissions are citywide, while sixplex locations are restricted. Plan changes, including HVAC or plumbing changes, remove the pre-approved submission option.
Where are you in your project?
Looking up an existing permit or older drawings? Find Toronto building permit records by address.