The rule changes by municipality
Start with the city where the property is located.
The City treats an opening change as regulated construction and requires the residential permit package and supporting drawings.
The permit question is tied to modifying the opening and structure rather than simple finish work.
Opening changes can affect structure, lintels and exterior-wall requirements. The permit is based on the construction change, not the product replacement alone.
The key distinction is whether the opening itself changes. Structural framing, lintels and property conditions can become part of the permit review when a new or larger opening is proposed.
The important distinction is whether the structural opening changes.
The permit trigger is tied to altering the opening and structure, not merely changing finishes or hardware.
For a detached, semi-detached or row house containing one dwelling unit, Toronto says replacement in an existing opening can be permit-exempt when the opening size and location stay the same, structural support is unaffected and no new exit is created.
Vaughan requires site/property context plus elevation and structural information when the opening changes.
Ontario sets the Building Code. Municipal rules, zoning, processes and project guidance still differ.