Oshawa, Ontario / Permit cost

What does a change of use permit cost?

See the published permit fee information BuildRules has verified for a change of use project in Oshawa, Ontario, with the source and limits visible.

Need the permit rules rather than just the fee? Read Oshawa change of use permit requirements and zoning checks

Check this for your address
Focused project answerLast verified Nov 9, 2026
Published fee information

Oshawa 2026 Building By-law Schedule B Part A item 4: Change of Use with no construction $160 flat. Where construction is proposed, fee follows the appropriate Part B alteration or construction class, plus any applicable other charges.

Use this as a municipal-fee reference, not as the total project budget. Design, engineering, related applications and construction costs are separate.

Scope before arithmetic

Make sure the fee belongs to your project.

The Building By-law 33-2009 section 6.2.4 requires existing/proposed use and occupancy details plus drawings showing floor layout, fire-resistance ratings and load-bearing capacities. Schedule C includes Applicable Law Checklist, possible architect/engineer General Review Commitment, owner undertaking, environmental documentation and site/location drawings where needed. Zoning, fire protection, egress, accessibility and separate business licensing remain address-specific. The $160 no-construction class is not total cost for work involving renovation.

Permit decisionIncreased-hazard change of use requires permit, even with no construction

The Building By-law 33-2009 section 6.2.4 requires existing/proposed use and occupancy details plus drawings showing floor layout, fire-resistance ratings and load-bearing capacities. Schedule C includes Applicable Law Checklist, possible architect/engineer General Review Commitment, owner undertaking, environmental documentation and site/location drawings where needed. Zoning, fire protection, egress, accessibility and separate business licensing remain address-specific. The $160 no-construction class is not total cost for work involving renovation.

Application route, if a permit appliesChoose Change of Use only for a no-construction use change

Identify existing approved use, future use and whether hazard classification increases. Confirm if construction is planned. Choose Change of Use only without construction; otherwise Alteration/Renovation. Check zoning, fire, exits, accessibility and any other authorizations. Prepare existing/proposed occupancy and fire-separation drawings and applicable-law forms. Budget $160 only for the no-construction permit class, pay any actual invoice and wait for approval before use.

Local checks and submission documents2026 no-construction fee $160; renovations use different fee

Current legal and proposed occupancy and hazard/use; Existing/proposed floor plans identifying fire-rated assemblies and exits; Existing and proposed wall/roof structural load-bearing conditions; Applicable Law Checklist and possibly architect/engineer General Review Commitment; Site/location plan and owner undertaking when applicable

Official sources behind this page

Permit decisionIncreased-hazard change of use requires permit, even with no construction

The Building By-law 33-2009 section 6.2.4 requires existing/proposed use and occupancy details plus drawings showing floor layout, fire-resistance ratings and load-bearing capacities. Schedule C includes Applicable Law Checklist, possible architect/engineer General Review Commitment, owner undertaking, environmental documentation and site/location drawings where needed. Zoning, fire protection, egress, accessibility and separate business licensing remain address-specific. The $160 no-construction class is not total cost for work involving renovation.

Official sourceCity of OshawaBuilding Permits · Residential permit triggers and project resources
Verified2026-11-09Open proof
Application route, if a permit appliesChoose Change of Use only for a no-construction use change

Identify existing approved use, future use and whether hazard classification increases. Confirm if construction is planned. Choose Change of Use only without construction; otherwise Alteration/Renovation. Check zoning, fire, exits, accessibility and any other authorizations. Prepare existing/proposed occupancy and fire-separation drawings and applicable-law forms. Budget $160 only for the no-construction permit class, pay any actual invoice and wait for approval before use.

Official sourceCity of OshawaBuilding Permits · Residential permit triggers and project resources
Verified2026-11-09Open proof
Local checks and submission documents2026 no-construction fee $160; renovations use different fee

Current legal and proposed occupancy and hazard/use; Existing/proposed floor plans identifying fire-rated assemblies and exits; Existing and proposed wall/roof structural load-bearing conditions; Applicable Law Checklist and possibly architect/engineer General Review Commitment; Site/location plan and owner undertaking when applicable

Official sourceCity of OshawaBuilding By-law 33-2009 as amended 118-2025: 2026 Schedule B · 2026 effective January 1 rates, minimum $160, Schedule C application documents
Verified2026-11-09Open proof
Change of Use filing splitNo-construction category vs alteration with construction

Oshawa specifies the Change of Use portal category only if no building work is proposed. When construction is part of the use change, the Alteration/Renovation application applies.

Official sourceCity of OshawaBuilding By-law 33-2009 as amended 118-2025: 2026 Schedule B · 2026 effective January 1 rates, minimum $160, Schedule C application documents
Verified2026-11-09Open proof

Need the full project answer?

The main guide keeps the permit trigger, zoning questions, documents, fees, timing and next steps together.

Open the change of use guide