Scope before arithmetic
Make sure the fee belongs to your project.
Underpinning changes how foundations transfer building loads to soil. Define each affected wall length and propose excavation and underpinning sequence with qualified structural design and site safety review. Foundation changes, shoring, basement headroom excavation, drains, adjacent buildings and utilities can require additional engineering and approvals. London B-7 also lists standalone excavation shoring at $13.53 per linear metre as a separate fee class. The City's Schedule B sets drawings/plans required according to building class; confirm qualifications and stages before work starts.
London explicitly lists underpinning foundations and basement headroom excavation as building-permit work. Professional structural design and appropriate shoring/support must be resolved before construction.
Identify walls and linear metres to underpin and whether the work also increases basement headroom. Have the load-bearing foundation, soil and temporary shoring assessed by a qualified structural professional. Prepare foundation plans, structural sections, phased construction sequence and drainage/service details. Apply for London's underpinning permit; request the assessed fee using $18.45/m and any applicable minimum/shoring charges. Do not excavate beneath foundations until approved construction drawings and required inspection stages are established.
Measured lengths and locations of foundation walls to underpin; Existing foundation, basement floor, site grade and nearby foundations; Engineered proposed sequence for excavation and support; Shoring, underpinning sections and structural load path; Drainage, underground utilities and impact on neighbouring structures
Official sources behind this page
London explicitly lists underpinning foundations and basement headroom excavation as building-permit work. Professional structural design and appropriate shoring/support must be resolved before construction.
Identify walls and linear metres to underpin and whether the work also increases basement headroom. Have the load-bearing foundation, soil and temporary shoring assessed by a qualified structural professional. Prepare foundation plans, structural sections, phased construction sequence and drainage/service details. Apply for London's underpinning permit; request the assessed fee using $18.45/m and any applicable minimum/shoring charges. Do not excavate beneath foundations until approved construction drawings and required inspection stages are established.
Measured lengths and locations of foundation walls to underpin; Existing foundation, basement floor, site grade and nearby foundations; Engineered proposed sequence for excavation and support; Shoring, underpinning sections and structural load path; Drainage, underground utilities and impact on neighbouring structures
Because underpinning changes the foundation support, confirm structural calculations, temporary support sequencing, nearby utilities/structures and staged inspections with London's Building Services.
Need the full project answer?
The main guide keeps the permit trigger, zoning questions, documents, fees, timing and next steps together.
Open the basement underpinning guide