London, Ontario / Permit timeline

How long does a interior alteration permit take?

See the published review timing BuildRules has verified for a interior alteration project in London, Ontario, including conditions and official references.

Need the permit rules rather than just the timeline? Read London interior alteration permit requirements and zoning checks

Check this for your address
Focused project answerLast verified Nov 9, 2026
Published timing

For a complete renovation permit for a qualifying detached/semi/townhouse, London lists initial review within 10 business days; other building types may require 15/20/30 business days. Corrections and approvals extend issuance.

A review target is one stage of the project. Preparation, responses, issuance and inspections can add separate time.

Plan the stages separately

The published period is not the whole project.

For a complete renovation permit for a qualifying detached/semi/townhouse, London lists initial review within 10 business days; other building types may require 15/20/30 business days. Corrections and approvals extend issuance.

Official sources behind this page

Permit decisionPermits for regulated interior changes, not cosmetic finish-only work

London distinguishes permit-required layout, structural, plumbing and room-use changes from painting, cabinets and other finishes. Residential Group C alteration fees follow area and minimum charge.

Official sourceCity of LondonBefore you apply for a building permit · Residential permit triggers, exemptions and review timelines
Verified2026-11-09Open proof
Application route, if a permit appliesSubmit existing/proposed layouts and affected systems

Separate decorating-only work from permit-required changes to walls, rooms, plumbing or insulation. Measure altered existing residential floor area in m² and identify applicable fee category. Prepare existing and proposed plans with beams, openings, HVAC/plumbing and safety details. Check if work creates an additional residential unit, which requires a different review. Submit permit when needed and arrange inspections before concealing regulated work.

Official sourceCity of LondonBefore you apply for a building permit · Residential permit triggers, exemptions and review timelines
Verified2026-11-09Open proof
Local checks and submission documents2026 residential alteration rate $3.68/m², minimum $260.37

Existing/proposed room layout with dimensions and occupancy; Walls, beams, posts and any proposed openings; Plumbing, heating, insulation, ventilation and fire safety changes; Stair and door/window egress details as applicable; Floor area to be altered and qualified designer details

Official sourceCity of LondonBuilding By-law B-7, Schedule A, effective March 1 2026 through February 28 2027 · 2026 fee schedule, residential alterations, demolition, structures, mechanical and plumbing
Verified2026-11-09Open proof
Published first-review period for complete applications10 business days for specified residential renovations, once complete

The general 10-business-day review stream applies to the City's specified house categories only. Commercial, multi-residential and larger buildings can fall under other published timelines. Confirm scope and classification.

Official sourceCity of LondonBefore you apply for a building permit · Residential permit triggers, exemptions and review timelines
Verified2026-11-09Open proof
Cosmetic exemption is limitedPainting, decorating and cabinets do not exempt structural/system work

London's before-apply permit list exempts cosmetic work, but lists interior alterations, basement finishing and changes to wall/rooms, insulation and plumbing as permit-required.

Official sourceCity of LondonBefore you apply for a building permit · Residential permit triggers, exemptions and review timelines
Verified2026-11-09Open proof

Need the full project answer?

The main guide keeps the permit trigger, zoning questions, documents, fees, timing and next steps together.

Open the interior alteration guide