Plan the stages separately
The published period is not the whole project.
For a complete renovation permit for a qualifying detached/semi/townhouse, London lists initial review within 10 business days; other building types may require 15/20/30 business days. Corrections and approvals extend issuance.
Official sources behind this page
London distinguishes permit-required layout, structural, plumbing and room-use changes from painting, cabinets and other finishes. Residential Group C alteration fees follow area and minimum charge.
Separate decorating-only work from permit-required changes to walls, rooms, plumbing or insulation. Measure altered existing residential floor area in m² and identify applicable fee category. Prepare existing and proposed plans with beams, openings, HVAC/plumbing and safety details. Check if work creates an additional residential unit, which requires a different review. Submit permit when needed and arrange inspections before concealing regulated work.
Existing/proposed room layout with dimensions and occupancy; Walls, beams, posts and any proposed openings; Plumbing, heating, insulation, ventilation and fire safety changes; Stair and door/window egress details as applicable; Floor area to be altered and qualified designer details
The general 10-business-day review stream applies to the City's specified house categories only. Commercial, multi-residential and larger buildings can fall under other published timelines. Confirm scope and classification.
London's before-apply permit list exempts cosmetic work, but lists interior alterations, basement finishing and changes to wall/rooms, insulation and plumbing as permit-required.