Scope before arithmetic
Make sure the fee belongs to your project.
Before committing to a new use, confirm London's Zoning By-law Z.-1 permits the proposed occupancy at that address. A change in use can affect exits, fire separation, accessibility, occupant load and mechanical ventilation even where no walls are moved. London Business Hub says Building Services and Fire Prevention may need to review commercial occupancy and fire inspections. The $260.37 no-construction fee is not an all-in cost where renovation or use-specific licences are required.
London lists changes to a building's purpose as a permit trigger and has a $260.37 no-construction change-of-use permit category. Other construction or life-safety approvals can be required.
Record current legally approved use and exact proposed new activity. Check zoning at the address with London's zoning office or Business Hub. Ask Building Services whether Change of Use without Construction or a construction/alteration permit applies. Prepare fire/life-safety, accessibility and layout documents for the new occupancy as instructed. Budget $260.37 only for the no-construction change-of-use class; obtain any separate permits before occupying.
Existing lawful occupancy and planned new use at this property; Floor area, occupant load and use-specific zoning requirements; Fire exits, alarm/sprinkler and fire separation changes; Accessibility and HVAC changes if use classification changes; Construction scope, even if no physical work is planned
Official sources behind this page
London lists changes to a building's purpose as a permit trigger and has a $260.37 no-construction change-of-use permit category. Other construction or life-safety approvals can be required.
Record current legally approved use and exact proposed new activity. Check zoning at the address with London's zoning office or Business Hub. Ask Building Services whether Change of Use without Construction or a construction/alteration permit applies. Prepare fire/life-safety, accessibility and layout documents for the new occupancy as instructed. Budget $260.37 only for the no-construction change-of-use class; obtain any separate permits before occupying.
Existing lawful occupancy and planned new use at this property; Floor area, occupant load and use-specific zoning requirements; Fire exits, alarm/sprinkler and fire separation changes; Accessibility and HVAC changes if use classification changes; Construction scope, even if no physical work is planned
B-7 2026 Schedule A 4(g) lists $260.37 flat for Permit for Change of Use when no construction is proposed. It is not the fee for an alteration requiring other permits.
Need the full project answer?
The main guide keeps the permit trigger, zoning questions, documents, fees, timing and next steps together.