Solar panels
Planning record, not municipal approval. Confirm the conditions and official requirements for your property.
0 of 5 ready
Your progress is saved in this browser. Project reference, date and notes stay in this tab until you leave.
What to do next
- Confirm whether building-mounted panel face area totals at least 5 m².
- Have an Ontario Professional Engineer assess structural capacity, uplift, snow loads and mounting.
- Prepare roof plan, structural letter, fastening details and manufacturer specifications.
- Submit the permit and budget $95 plus refundable $250 or $1,000 depending on building category.
- Confirm separate electrical approvals, obtain final engineer certification and City inspection to trigger deposit refund.
Official sources behind this page
City guidance requires a building permit at aggregate building-mounted face area of 5 m² or more. Structural design and certification by an Ontario Professional Engineer are required.
Provide panel locations, engineer roof capacity letter, fastening/rail and reinforcement plans where needed, and manufacturer specifications. An engineer later certifies the completed installation.
Pay $95 City permit plus refundable $250 for applicable homes or $1,000 for most other buildings. Final approved inspection releases deposit. Confirm independent ESA electrical approval.
Existing roof loads and panel fastener systems must be evaluated by a Professional Engineer of Ontario; the engineer must certify the completed installation to the City inspector.
Refundable fee depends on building type and is returned automatically when the final building inspection is approved, not when a permit is initially issued.