Cambridge, Ontario / Permit cost

What does a new house permit cost?

See the published permit fee information BuildRules has verified for a new house project in Cambridge, Ontario, with the source and limits visible.

Check this for your address
Focused project answerLast verified Oct 29, 2026
Published fee information

City-issued 2026 simplified fee schedule, p.5: new single-detached/semi/row/townhouse/duplex construction is assessed at $1.65/ft², minimum $143. Separate zoning-review charges vary with new dwelling/infill classifications. For applicable new infill homes, the schedule also lists a $4,000 grading deposit per lot. These are not included in the quoted base building-permit component.

Use this as a municipal-fee reference, not as the total project budget. Design, engineering, related applications and construction costs are separate.

Scope before arithmetic

Make sure the fee belongs to your project.

The permit statement above comes from the linked municipal guidance. The preparation items below help define your scope; confirm the final application checklist, property constraints and any separate trade approvals with the municipality.

Published municipal guidanceCheck the scope and stated conditions

Cambridge publishes a residential housing permit process with application forms, designer responsibility, site and grading information, and building drawings appropriate to the project.

2026 permit-fee evidence$1.65/sq. ft. for new house, $143 minimum

2026 City-issued fee schedule p.5: new house building-permit component. Zoning charges and potentially refundable grading deposit (new infill $4,000 per lot) are separate.

Official sources behind this page

Published municipal guidanceCheck the scope and stated conditions

Cambridge publishes a residential housing permit process with application forms, designer responsibility, site and grading information, and building drawings appropriate to the project.

Official sourceCity of CambridgeBuilding Permits · Permit triggers for structures, garages, openings and retaining walls
Verified2026-10-01Open proof
2026 permit-fee evidence$1.65/sq. ft. for new house, $143 minimum

2026 City-issued fee schedule p.5: new house building-permit component. Zoning charges and potentially refundable grading deposit (new infill $4,000 per lot) are separate.

Official sourceCity of Cambridge Building Services2026 Simplified Building Permit Fee Schedule (City-issued PDF supplied directly to BuildRules; publicly linked page is the Building Permits landing page) · Schedule effective January 1, 2026; pp. 1–2 (fee method), 5 (Group C), 7 (accessory structures), 8 (renovations), 9–11 (other permits). PDF attached to official city email of Oct 29; original attachment held privately.
Verified2026-10-29Open proof

Need the full project answer?

The main guide keeps the permit trigger, zoning questions, documents, fees, timing and next steps together.

Open the new house guide