BuildRules does not yet have a reviewed answer for this project in this municipality. Here is how to move forward.
Property-specific permit determination: not confirmed
YOUR ACTION PLAN
What to check before you build
PROVINCIAL RULE · ONTARIO
A shed of 15 m² or less: 5 conditions for the permit exemption
Conditional exemptionOntario’s 2024 Building Code, Division C, Article 1.3.1.1.(6), exempts a shed from the building permit requirement only when every condition below is met.
- Gross area is no more than 15 m².
- One storey maximum.
- Not attached to a building or any other structure.
- Used only for storage ancillary to the main building on the lot.
- No plumbing.
Important: a permit exemption is not permission to build. Check local zoning, height, setbacks and lot coverage, plus any separate approvals that may apply to your property.
Read the provincial Building Code provisionLocal requirements still need verification
No current-source local rule is published for this work here. This does not mean no permit is needed or the work is approved.
- 01
Define the work clearly
What are the shed dimensions, height, use and setback from lot lines?
- 02
Confirm zoning and site constraints
Do zoning, protected lands or separate approvals affect this project?
- 03
Get application requirements
What drawings, supporting documents and inspections are required?
- 04
Secure required approvals before starting
Confirm which drawings, fees, approvals and inspections apply. Do not assume an exemption.